Sigenergy declares its storage systems section 14a compliant and describes the connection in a two-page guide: a contact input on the Energy Controller, an option in the app. But the guide contains two places that deviate from the Bundesnetzagentur's ruling. Both should be clarified with the manufacturer before commissioning.
In March 2025 Sigenergy declared: “Sigenergy storage systems are section 14a EnWG compliant.” The accompanying guide describes two steps:
The guide names no further Sigenergy hardware. The “14a receiver” – the control box or another control device – comes from the metering point operator.
On the control logic the guide says: “In accordance with the requirements of 14a, Sigenergy controls the feed-in power of the grid connection and not the individual devices.”
Section 14a does not concern feed-in. The ruling limits the “effective grid consumption” (clause 2.3) and covers storage only “with regard to electricity withdrawal (charging)” (clause 2.4.1). “Feed-in power” is probably a translation error for the power at the grid connection overall. Have Sigenergy confirm this and check it at commissioning: switch the contact and see at the meter whether grid consumption drops.
For control via energy management, Sigenergy gives two formulas with a simultaneity factor. The first matches the ruling: 4.2 kW plus (number − 1) × simultaneity factor × 4.2 kW. The second uses as its first term the maximum of 0.4 × the total power of the AC chargers, the DC chargers and the SigenStor. Both cases are labelled “room cooling installations” below and above 11 kW.
Clause 4.5.2 of the ruling provides for the factor 0.4 only when heat pumps or room cooling installations above 11 kW are part of the control, and then on their total power – not on chargers or storage. Because the contact on DI5 only signals “limit now”, the system calculates the value it keeps during curtailment itself. Which formula the software actually uses should therefore be clarified before commissioning.
The guide describes the contact route via DI5; it does not mention an EEBUS connection. If the metering point operator's control box only controls digitally, clarify this before ordering. Which control the responsible grid operator provides for is set out in its technical connection conditions.
According to Sigenergy's instructions (version 1.0, March 2025), the 14a receiver is connected to DI5 and GND of the COM port on the Sigenergy Energy Controller (pins 9 and 10) and the EnWG14a option is selected in the app. The instructions name no additional Sigenergy hardware; the control box itself is provided by the metering point operator.
The instructions say that Sigenergy controls “the feed-in power of the grid connection and not the individual devices”. Section 14a, however, concerns consumption from the grid: the ruling limits the effective grid consumption, for storage the withdrawal. Whether this is a translation error should be clarified with Sigenergy.
Sigenergy gives a formula with a simultaneity factor and applies the factor 0.4 to the power of the chargers and the SigenStor. The ruling provides for the factor 0.4 only for heat pumps and room cooling installations above 11 kW; otherwise the first term is 4.2 kW. This too should be clarified before commissioning.
The manufacturer information comes exclusively from the manufacturer's own documents, each with its date and the date it was checked. Manufacturer documents change with every firmware release; what counts is the version valid at the time of installation. Quotations from German documents are our translation.
This article reproduces manufacturer information; it replaces neither Sigenergy's documentation nor the technical connection conditions of your grid operator. Connection and registration are reserved for a registered electrical contractor. Haag Automation has no business relationship with Sigenergy.