Technical article · Manufacturers

Sigenergy and section 14a EnWG

Sigenergy declares its storage systems section 14a compliant and describes the connection in a two-page guide: a contact input on the Energy Controller, an option in the app. But the guide contains two places that deviate from the Bundesnetzagentur's ruling. Both should be clarified with the manufacturer before commissioning.

Devices
Sigenergy storage systems with Sigenergy Energy Controller
Connection
DI5 and GND on the Energy Controller's COM port, pins 9 and 10
Setting
EnWG14a option in the app
Manufacturer source
guide “Wie aktiviert man die EnWG 14a Funktion im Sigenergy-System?”, version 1.0, March 2025
Status
October 2026 · primary sources below, with the date each was checked
Author
Julian Haag, state-certified electrical engineering technician

Connection and setting

In March 2025 Sigenergy declared: “Sigenergy storage systems are section 14a EnWG compliant.” The accompanying guide describes two steps:

  1. Wiring. “Connect the DI5 and GND terminals of the COM port of the Sigenergy Energy Controller to the 14a receiver”; the pins are 9 and 10.
  2. App. Select the “EnWG14a” option in the app.

The guide names no further Sigenergy hardware. The “14a receiver” – the control box or another control device – comes from the metering point operator.

First point: feed-in or consumption?

On the control logic the guide says: “In accordance with the requirements of 14a, Sigenergy controls the feed-in power of the grid connection and not the individual devices.”

Section 14a does not concern feed-in. The ruling limits the “effective grid consumption” (clause 2.3) and covers storage only “with regard to electricity withdrawal (charging)” (clause 2.4.1). “Feed-in power” is probably a translation error for the power at the grid connection overall. Have Sigenergy confirm this and check it at commissioning: switch the contact and see at the meter whether grid consumption drops.

Second point: the minimum power

For control via energy management, Sigenergy gives two formulas with a simultaneity factor. The first matches the ruling: 4.2 kW plus (number − 1) × simultaneity factor × 4.2 kW. The second uses as its first term the maximum of 0.4 × the total power of the AC chargers, the DC chargers and the SigenStor. Both cases are labelled “room cooling installations” below and above 11 kW.

Clause 4.5.2 of the ruling provides for the factor 0.4 only when heat pumps or room cooling installations above 11 kW are part of the control, and then on their total power – not on chargers or storage. Because the contact on DI5 only signals “limit now”, the system calculates the value it keeps during curtailment itself. Which formula the software actually uses should therefore be clarified before commissioning.

Sigenergy: commissioning the EnWG14a function in four steps Four numbered steps one below the other. First, clarify with Sigenergy whether the system limits consumption and which formula it uses. Second, wire the 14a receiver contact to DI5 and GND on the COM port of the Energy Controller, pins 9 and 10. Third, select the EnWG14a option in the app. Fourth, switch the contact and check at the meter whether grid consumption drops. 1 Clarify first Does the system limit consumption (notfeed-in)? Which formula does it use? 2 Wire 14a receiver contact to DI5 and GND,COM port of the Energy Controller, pins 9/10 3 Configure Select the “EnWG14a” option in the app 4 Check Switch the contact: does grid consumptiondrop at the meter? Record the result
Steps 2 and 3 are as given in Sigenergy’s instructions (version 1.0, March 2025). Steps 1 and 4 follow from the two deviations from the determination described above.

And EEBUS?

The guide describes the contact route via DI5; it does not mention an EEBUS connection. If the metering point operator's control box only controls digitally, clarify this before ordering. Which control the responsible grid operator provides for is set out in its technical connection conditions.

Frequently asked questions

Can a Sigenergy system meet section 14a without additional material?

According to Sigenergy's instructions (version 1.0, March 2025), the 14a receiver is connected to DI5 and GND of the COM port on the Sigenergy Energy Controller (pins 9 and 10) and the EnWG14a option is selected in the app. The instructions name no additional Sigenergy hardware; the control box itself is provided by the metering point operator.

Does Sigenergy control feed-in or grid consumption under section 14a?

The instructions say that Sigenergy controls “the feed-in power of the grid connection and not the individual devices”. Section 14a, however, concerns consumption from the grid: the ruling limits the effective grid consumption, for storage the withdrawal. Whether this is a translation error should be clarified with Sigenergy.

Which minimum power does Sigenergy calculate?

Sigenergy gives a formula with a simultaneity factor and applies the factor 0.4 to the power of the chargers and the SigenStor. The ruling provides for the factor 0.4 only for heat pumps and room cooling installations above 11 kW; otherwise the first term is 4.2 kW. This too should be clarified before commissioning.

Sources

The manufacturer information comes exclusively from the manufacturer's own documents, each with its date and the date it was checked. Manufacturer documents change with every firmware release; what counts is the version valid at the time of installation. Quotations from German documents are our translation.

This article reproduces manufacturer information; it replaces neither Sigenergy's documentation nor the technical connection conditions of your grid operator. Connection and registration are reserved for a registered electrical contractor. Haag Automation has no business relationship with Sigenergy.

Planning PV with battery storage and want control, grid consumption and metering kept cleanly apart? Write to me – the initial consultation is free.