Technical article · Grid operator
Section 14a EnWG at Netze ODR
The technical minimum requirements of Netze ODR GmbH from Ellwangen visibly follow the same template as those of Netze BW, down to individual sentences. That is exactly why a close look pays off: in several places it deviates, at the meter location, in existing installations and above all in grid fees. This page collects what Netze ODR itself writes, each with document and date checked.
Your electricity bill shows which grid operator is responsible for your connection. The basics are in the guide to section 14a EnWG; Netze BW's requirements are in the article Section 14a EnWG at Netze BW.
The documents
In its TAB supplement Netze ODR describes itself as “a company of EnBW Ostwürttemberg DonauRies AG (ODR)”. Three documents are decisive for section 14a:
- the technical minimum requirements for controlling electrical installations (TMA), version 1.0 of 18 August 2026, which cover section 14a together with grid security management for generation plants,
- the supplements to the TAB 2023 for low voltage, valid from 1 February 2025, with its own section on controllable consumption devices,
- the final 2026 price sheet, version 2.0 of 17 December 2025.
On top of that there is a detailed FAQ on the website, which is more specific than the documents in a few places.
What counts, and what is not possible
Netze ODR adopts the four groups of the determination with more than 4.2 kW connected load at low voltage: private charging points, heat pump heating including supplementary and emergency heating, room cooling systems and battery storage with regard to charging. Night storage heaters are not affected. Exempt are charging points of institutions with special rights under section 35 of the German road traffic regulations and heat pumps and air conditioners for commercial, operationally necessary purposes or in critical infrastructure. Four points from the FAQ matter in practice:
- Not controllable is not an option. Asked whether an affected system can be installed without control, Netze ODR answers “No”. Only proof of controllability, confirmed and registered by the electrician, entitles the system to commissioning and to reduced grid fees.
- Curtailment to zero is allowed. Under the Federal Network Agency's rules at least 4.2 kW are permanently available, but the operator is free to implement controllability so that the system is regulated to 0. That is the route for devices that can only switch on and off.
- Storage: according to the FAQ, every storage system commissioned from 2024 with a theoretical charging power of at least 4.2 kW must be registered and installed according to the TMA. The determination itself speaks of more than 4.2 kW; in case of doubt, Netze ODR clarifies.
- Moving: if a wallbox is reconnected within the same connected property, for example from meter A to meter B in the underground car park, existing-system protection applies. Moving to another house counts as decommissioning and a new installation; the system must then be made controllable.
Registration and module choice
The electrician registers the new system using the registration and commissioning form and confirms its controllability; for existing systems this is done as a change notification. Netze ODR reports the entitlement to the supplier, who shows the reduced grid fees on the bill. Changes affecting power and permanent decommissioning must be notified in advance.
One special feature is in the TAB supplement: the module is already chosen at registration, and this decision “has direct consequences for the installation set-up”. With module 1 a shared meter measures the controllable system and the other loads. With module 2 the controllable system “must be measured via a separate meter”. Anyone who wants module 2 should plan the second meter location from the start.
The meter location according to the TMA
Section 6 of the TMA sets out the requirements for controllable consumption devices. The basic rules:
- Terminal strip and RJ-45 always: the control signal terminal strip and RJ-45 socket must always be provided as the interface to the controllable consumption device. Analogue control uses terminals 5 and 6 of the terminal strip.
- Digital means EEBUS: the minimum standard is an interface based on VDE-AR-E 2829-6-1 and the VDE FNN guidance in the EEBUS version, explicitly also for bidirectional charging equipment and stationary storage. Netze ODR recommends paying attention to updatability.
- Contacts for 5–250 V and 1 A. If that is not enough or the logic must be inverted, coupling relays belong in the customer installation, for example in the distribution field; they are supplied “with metered energy”. That is also where the signal is multiplied.
- Space: with a three-point smart metering system and control box, the 8-module space for supplementary applications is undersized; a control device field, an APZ space, an additional space for supplementary applications or a small distribution board with at least 10 modules is needed. A new control device field is sealable and has at least one 12-module DIN rail.
- Data cable: if control runs via the control device field, a data cable of at least Cat 5 between the space for supplementary applications and the control device field is mandatory.
For new installations the TMA names two variants for housing the control box: a sealable universal surface-mounted mini distribution board on the third DIN-rail mount of an existing meter field, or the distribution field directly in the APZ field. Both need an unmetered power supply with a three-pole socket connector with 5.08 mm pitch and a communication line with RJ-45 socket.
At the end the TMA requires a declaration: the operational wiring of both transmission paths, analogue and digital, must be completed up to the controllable consumption devices and declared in writing by a registered electrical installation company under section 13 of the German low-voltage connection ordinance.
A note from the part on generation plants also concerns the smart meter gateway: Netze ODR connects its meters via public mobile networks. If reception at the meter location is insufficient, the customer must cooperate, for example with an antenna cable; with flush-mounted meter cabinets and covers above the cabinet, an M32 conduit for the antenna cable must be provided.
In an existing meter cabinet
Where the standard is not possible, the TMA refers to the BDEW application guide and names two routes for three-point meter locations:
- The bottom distribution field: if a distribution field exists, its bottom DIN rail becomes the additional space for supplementary applications, with the same requirements as the space for supplementary applications (partitioning, sealable, unmetered power supply, RJ-45).
- The external control device location: if that is not possible, a control device location is set up outside the meter cabinet in its immediate vicinity, in the same room, with the functional areas “zRfZ” and “distribution field” and an enclosure according to DIN VDE 60670-24.
The BKE-AZ adapter plate that Netze BW names as a third route does not appear in Netze ODR's TMA. All three routes at Netze BW are in the article Control box in an old meter cabinet.
Grid fees 2026
Anyone who makes no choice is billed under module 1. The prices from the final 2026 price sheet, incl. VAT:
| Module | Price | Requirement |
|---|---|---|
| Module 1 – flat rate | credit 132.39 €/year | default; only with the standard grid fee or module 3; never below 0.00 € |
| Module 2 – energy price | 2.80 ct/kWh instead of 6.99 ct/kWh | separate metering point, no power metering |
| Module 3 – low tariff, April–September 11 am–5 pm | 2.80 ct/kWh | only with module 1 and a smart metering system; October to March standard tariff all day |
| Module 3 – standard tariff, April–September 5–11 am and 5–10 pm | 6.99 ct/kWh | |
| Module 3 – high tariff, April–September midnight–5 am and 10 pm–midnight | 12.11 ct/kWh |
The standing charge is 78.18 € a year incl. VAT. Two things stand out. At Netze ODR, module 3 applies in 2026 only in the summer half-year; at Netze BW in all four quarters. And the high tariff is at night, from 10 pm to 5 am, the low tariff in the afternoon. A wallbox that charges at night therefore becomes more expensive with module 3 in summer, one that charges in the afternoon with the sun cheaper.
Which module pays off at which consumption is in the article Section 14a: module 1, 2 or 3?; the grid fee calculator works with your own figures.
Existing systems
The FAQ distinguishes three cases:
- Systems that went into operation before 2024 and already receive a reduced grid fee under the old section 14a must have switched to the new model by 1 January 2029. Switching earlier is voluntary; there is no way back.
- Systems that went into operation before 2024 and receive no reduced grid fee do not have to switch but may, again without a way back.
- Old section 14a systems that are not controllable consumption devices in the new sense lose their reduction from 1 January 2029 or on any change. Night storage heaters keep the reduction granted in 2023 as long as nothing is converted.
The supplier orders the switch of an existing system with an agreement at the customer's request. The general rules are in the article Section 14a EnWG for existing systems.
Netze ODR, Netze BW and NHF compared
| Netze ODR | Netze BW | NHF / NHL | |
|---|---|---|---|
| Interface | terminal strip and RJ-45 always | RJ-45 always, terminal strip for analogue control | customer-owned 230 V coupling relay |
| Routes in existing cabinets | two | three (with BKE-AZ) | four cases by meter location |
| TMA version | August 2026 | April 2026 | December 2023 |
| Module 1, incl. VAT | 132.39 €/year | 147.56 €/year | 152.83 €/year |
| Module 3 low tariff | 11 am–5 pm, April–September only | 10 am–2 pm, all year | midnight–6 am, all year |
The details on the other two: Section 14a EnWG at Netze BW and Section 14a EnWG at NHF and NHL in Heilbronn.
Frequently asked questions
Must a terminal strip always be installed at Netze ODR?
Yes. According to Netze ODR's technical minimum requirements of August 2026, the control signal terminal strip and the RJ-45 socket must always be provided as the interface to the controllable consumption device. Analogue control uses terminals 5 and 6, digital control the RJ-45 socket with EEBUS.
May my wallbox be curtailed to zero at Netze ODR?
Yes, if you design it that way. Netze ODR writes that under the Federal Network Agency's rules at least 4.2 kW are permanently available, but that you are free to implement controllability so that the system is regulated to 0. This concerns systems that cannot be dimmed but only switched off.
What applies to module 3 at Netze ODR?
According to the 2026 price sheet, the three tariff levels apply only from April to September: low tariff from 11 am to 5 pm at 2.80 cents per kilowatt hour incl. VAT, standard tariff from 5 to 11 am and 5 to 10 pm at 6.99 cents, high tariff from midnight to 5 am and 10 pm to midnight at 12.11 cents. From October to March the standard tariff applies all day. Module 3 can only be chosen together with module 1 and a smart metering system.
How high is the module 1 credit at Netze ODR?
111.25 euros a year net, 132.39 euros incl. VAT, according to the final 2026 price sheet. The credit can reduce the grid fee of a metering point to 0.00 euros at most. Anyone who chooses no module is billed under module 1.
What happens to the wallbox when I move?
If it stays in the same connected property, for example when it is reconnected from one meter to another in the underground car park of an apartment building, existing-system protection applies according to Netze ODR. Moving to another house counts as decommissioning and a new installation, and the system must then be made controllable.
Sources
All statements come from Netze ODR's documents and website, each with the date it was checked. In case of deviations, the grid operator's documents in their current version apply. The source documents are in German; quotations are my translation.
- TMA Netze ODR – technical minimum requirements for controlling electrical installations (PDF) Version 1.0 of 18.08.2026; section 4 (contacts, coupling relay, control device field), 5.2 (mobile network), 6 (terminal strip and RJ-45, EEBUS, terminals 5 and 6, new-installation variants, two routes in existing cabinets, declaration under section 13 NAV). Checked on 08.10.2026.
- TAB Netze ODR – supplements to TAB 2023 low voltage (PDF) As of January 2025, valid from 01.02.2025; section 9.2 (module choice at registration, installation set-up for modules 1 and 2). Checked on 08.10.2026.
- Price sheet Netze ODR – final price sheets electricity 2026 (PDF) Version 2.0, 17.12.2025; modules 1 to 3, module 3 tariff times, standard grid fee. Checked on 08.10.2026.
- Website Netze ODR – new section 14a EnWG rules FAQ: affected systems, controllability mandatory, curtailment to 0, storage, moving, registration, existing systems. Checked on 08.10.2026.
Haag Automation has no business relationship with Netze ODR. The grid operator's documents and information are binding.
You are planning a heat pump, wallbox or battery in Netze ODR's grid area and need the single-line diagram for the registration? I can draw it for you – or write to me about control and energy management.