Technical article · Grid operators

Section 14a EnWG at Netze BW

The Bundesnetzagentur's ruling applies nationwide; the grid operator fills in the details. This page collects what Netze BW requires in its own documents for controllable consumption devices – from registration and the meter position to the duties that only begin after commissioning. Every statement with its document and the date it was checked.

Applies to
low-voltage connections in the Netze BW GmbH grid area
Registration
registered electrical contractor via the customer portal
Meter position
RJ-45 socket always, EEBus as minimum standard, at least 10 modules
Grid fee 2026
module 1 by default: €147.56 a year incl. VAT
Documents
technical minimum requirements 1.0, general terms, 2026 price sheet
Status
October 2026 · primary sources below, with the date each was checked
Author
Julian Haag, state-certified electrical engineering technician

Which grid operator is responsible for your connection is shown on your electricity bill. The basics that are the same for every operator are in the section 14a EnWG guide.

What counts as a controllable consumption device

Netze BW adopts the categories of the ruling: private charging points, battery storage, heat pump heating including auxiliary and emergency heaters, and room cooling installations, each above 4.2 kW, connected to the low-voltage grid and commissioned from 1 January 2024. Two clarifications from its documents matter in practice:

And for everything below: “Consumption devices of 4.2 kW or less must still be reported to Netze BW and may not participate under the section 14a EnWG ruling.” The threshold decides controllability, not reporting – covered in detail in The 4.2 kW in section 14a EnWG.

Registration: what the electrician takes care of

According to Netze BW, the operator does not need to do anything. Registration lies with the registered electrical contractor, and Netze BW explains why: only they can “ensure the implementation of the technical connection conditions (TAB) and the technical minimum requirements (TMA)”. The electrician confirms compliance with both in the customer portal.

The meter position under the technical minimum requirements

Since 1 April 2026 Netze BW has bundled its requirements in the technical minimum requirements for controlling electrical installations, version 1.0. The basic rules:

Exactly where socket and terminal strip go depends on the type of meter position. The minimum requirements distinguish nine cases; in summary:

Location of RJ-45 socket and control signal terminal strip under Netze BW TMA, section 6.2
Meter positionLocation of socket and terminal strip
Plug-in meter position or three-point meter position, no further panelin the installation-side connection space of the transfer meter
Three-point meter position with BKE-AZ adapter plate (at least 12 modules)in the installation-side connection space of the transfer meter; the metering point operator fits a plug-in meter
Meter position with control device panel in three-point designin the installation-side connection space of the control device panel; small distribution board with DIN rail required
Meter position with control device panel in the new design (mounting plate and DIN rail)in the installation-side connection space of the control device panel
Semi-indirect meteringalways with control device panel – with small distribution board or in the new design

If there is no room in an existing cabinet, Netze BW names three routes – the distribution panel, the adapter plate or a control device location outside the meter cabinet. All three in detail: Control box in an old meter cabinet.

And the radio ripple control receiver?

The question comes up regularly because many meter cabinets still have one. For section 14a, Netze BW names exactly two variants: grid-oriented control via a control box “connected to a smart metering system (smart meter)”, and, as a transitional measure, preventive control via a fixed timer. A radio ripple control receiver is not one of them.

It appears in two other places in Netze BW's requirements:

How Netze BW controls

Preventive means: fixed time windows via a timer, “for example between 12:30 and 13:00”, as a transitional solution until 31 December 2028 at the latest. Netze BW must announce the start in advance in text form and name the grid area. Grid-oriented means: only when needed, but “at any time and without prior notice”.

Two sentences in Netze BW's documents do not seem to fit together at first. The web page says “a minimum power is always guaranteed and a complete shutdown does not take place”. The general terms say: if an installation cannot technically reduce to the requested value, it must go to the next lower value “that is technically possible and can also be zero”. Both are true – the minimum power exists for devices that can throttle. A device that only knows on and off stands still during curtailment.

On a wallbox and heat pump at the same connection, Netze BW says: “With a control command we merely transmit a maximum power value for your section 14a installations. Implementing and distributing the available power across your section 14a installations is the responsibility of the operators.” That describes control via an energy management system; the general terms give the operator a choice per installation between this and direct control, in which each device gets its own setpoint.

And if it happens too often? If Netze BW has to curtail too frequently at one point, it says it is obliged “to expand the grid at that point within a certain period”. Anyone who thinks that applies to them needs their own records – why and how is covered in What curtailment does in practice.

Grid fees 2026 at Netze BW

Without an application, module 1 applies. For module 2 or 3 the operator applies to the electricity supplier, not to Netze BW. The prices from the 2026 price sheet:

Netze BW section 14a grid fees 2026, incl. VAT, consumption without load profile metering
ModulePriceRequirement
Module 1 – flat ratecredit of €147.56/yeardefault without application; no separate meter
Module 2 – energy price3.61 ct/kWh instead of 9.01 ct/kWhmetered separately, own market location, no power metering
Module 3 – low tariff, 10:00–14:003.61 ct/kWhonly together with module 1; smart metering system; in all four quarters of 2026
Module 3 – standard tariff, 0:00–10:00, 14:00–17:00, 22:00–24:009.01 ct/kWh
Module 3 – high tariff, 17:00–22:0013.16 ct/kWh

Two rules from the general terms belong with this: module 1 cannot push the grid fee at a market location below €0.00. And a module change never applies retroactively, only from notification to the grid operator and the supplier at the earliest – whichever is later.

Which module pays off at which consumption, with exactly these prices: Section 14a: module 1, 2 or 3? – and with your own values in the section 14a grid fee calculator.

Existing installations at Netze BW

For installations commissioned before 1 January 2024, Netze BW distinguishes three cases:

Whether an installation has an existing section 14a agreement can, according to Netze BW, be seen in the electricity supply contract. With an existing agreement, the supplier initiates the switch; without one, the electrician first checks whether the installation meets the technical requirements. Night storage heaters keep permanent grandfathering; a voluntary switch is not possible for them.

Whether switching pays off, with Netze BW's legacy price for heat pumps and a worked example: Section 14a EnWG for existing systems.

Duties after commissioning

Commissioning is where it really starts. Netze BW's general terms list what the operator owes on an ongoing basis:

For anyone running their wallbox or heat pump on spot prices with Home Assistant or another energy manager, the second point is the decisive one: your own automation has to give way to the control command. And the third point is a good reason to log the interventions – a system that measures every load anyway can do it on the side.

The agreement can be terminated with one month's notice to the end of a month. Because participation is mandatory, however, that can mean the installation has to be taken out of operation.

Frequently asked questions

How is a controllable consumption device registered with Netze BW?

Through a registered electrical contractor. The contractor reports commissioning in the Netze BW customer portal and confirms there that the installation complies with the technical connection conditions and the technical minimum requirements. According to Netze BW, the operator does not have to do anything else. This also applies to a mobile wallbox on a CEE socket.

What does Netze BW require in the meter cabinet for section 14a?

An RJ-45 socket as the interface must always be provided; if analogue control is also used, a control signal terminal strip goes next to it. EEBus is the minimum standard for digital control. With a smart metering system and control box, the 8-module space for additional applications is not enough; a control device panel, an APZ space, an additional space for additional applications or a small distribution board with at least 10 modules is needed.

Do you need a second meter for section 14a with Netze BW?

Only for module 2. Netze BW grants the reduced energy price only if the consumption of the controllable device is metered separately and billed at its own market location. Module 1, which applies without an application, needs no separate meter. Module 3 requires a smart metering system and is only possible together with module 1.

Does Netze BW control section 14a devices via a radio ripple control receiver?

No. For section 14a, Netze BW names two variants: grid-oriented control via a control box on the smart metering system and, as a transitional measure until the end of 2028 at the latest, preventive control via a fixed timer. Radio ripple control receivers appear in its requirements for PV systems from 25 to under 100 kW and in older installations with peak/off-peak switching for storage heaters.

Sources

All statements come from Netze BW's documents, each with the date it was checked. Netze BW updates its requirements; what counts is the version valid at registration. Quotations from German documents are our translation.

This article summarises Netze BW's documents; it replaces neither them nor the technical connection conditions. Connection and registration are reserved for a registered electrical contractor. Haag Automation is not part of Netze BW and does not speak for it.

Planning in the Netze BW grid area and need the single-line diagram for registration? I can draw it for you – or write to me about control and energy management.