Three routes lead from the grid operator to the device: a volt-free contact, a digital interface, or an energy management system in between. Which of them counts is not for the manufacturer to decide alone. This page sets out the three routes, the recommended minimum standard and the five questions to settle before buying – a procedure that lets you place any device.
At the meter position sits the control unit – colloquially the control box. It receives the grid operator's signal and passes it on. There are three variants for this, and every device must master at least one of them.
The third route is why the question “can device X do it?” often misses the point: a device with no control interface at all can still run in a section 14a compliant installation if an energy management system sits in front of it and limits the power.
For the digital variant there has been a clear recommendation since March 2025. VDE FNN drew it up on behalf of the federal network agency – ruling BK6-22-300 refers to it in tenor clause 2a. The governing sentence, in the German original:
„Als Mindeststandard wurde sich dabei mehrheitlich für die VDE-AR-E 2829-6-1 mit der verpflichtenden Umsetzung des EEBUS-Kommunikationsprotokolls ausgesprochen.“ – The minimum standard agreed by majority is VDE-AR-E 2829-6-1 with mandatory implementation of the EEBUS communication protocol.
Among the reasons given: EEBUS is available free of charge as a published standard, the exchange of SKI values simplifies establishing the connection during commissioning in the field, and the German federal office for information security has entered a standardisation partnership with the EEBUS Initiative. Two things are expressly still in progress at the time of the recommendation: full plug-and-play capability and an interoperable conformity assessment.
What this means in practice: anyone choosing a device today should put EEBUS on the list – even if their own grid operator currently still works with relay contacts. A device with EEBUS can do both; one without has to be retrofitted or replaced when the operator's requirement changes.
In this order, because each one shapes the next.
“Section 14a compliant” on a data sheet says little by itself. A statement you can plan on names three things: which model ranges exactly are meant, which connection options exist individually, and which document revision the statement carries.
One example that meets this form is the conformity document by go-e for the wallbox series Gemini, Gemini 2.0, PRO and CORE: it lists the affected models by name, distinguishes between versions with and without a volt-free input – the Gemini flex lacks one, which is why control over the network is recommended there –, describes each connection method separately and carries a version number. That is what an electrician can work with.
Even a good manufacturer statement is not proof towards the grid operator. It says what the device can do – not whether the operator accepts that particular variant. Both have to match, and it gets settled before ordering, not on installation day.
Modbus is widespread, well documented and present in many heat pumps and inverters. The only question is where it sits.
Between the control unit and the device, Modbus is not the recommended minimum standard – EEBUS is. A grid operator following the recommendation expects EEBUS there.
Between an energy management system and the device, Modbus is entirely unproblematic and common practice. The EMS translates: upwards it speaks the required interface, downwards whatever the device understands. That is precisely the route by which older devices can still be integrated – and the point at which Home Assistant and comparable systems come into play.
Instead of all this, the obvious move would have been a table: device, tick, done. I have left it out, and the reason is at the same time why this page is built the way it is.
Whether a device can be operated controllably within the meaning of section 14a depends on four things, only the first of which is contained in the product name: the model range, the firmware revision, the variant the responsible grid operator supports, and how the device is connected – directly or through an energy management system. A table that ignores this is imprecise the moment it is published and wrong six months later.
The useful answer is therefore not a list but the procedure above. Walk through it once and you can place any device – including the one that only reaches the market next year.
Where a manufacturer publishes reliable information, the procedure is applied on a page of its own, with the date of every document – thirteen manufacturers at a glance: Section 14a by manufacturer.
One of three: a volt-free input for the control box's relay contacts, a digital interface, or a connection to an energy management system that is itself controlled. For the digital variant, VDE FNN issued a minimum standard in March 2025: VDE-AR-E 2829-6-1 with mandatory implementation of the EEBUS communication protocol.
It depends on which link it sits on. Between the control unit and the device, Modbus is not the recommended minimum standard – EEBUS is. Between an energy management system and the device behind it, Modbus is common and unproblematic: in that case the energy management system has to meet the requirement, not the individual device.
As a starting point yes, as proof no. What decides is which variant the responsible grid operator actually supports – some still work with relay contacts, others rely on the digital interface. A dependable manufacturer statement names the specific model ranges, the document revision and each supported connection method separately. If one of those is missing, the statement is too vague to plan on.
For section 14a, usually yes, if the grid operator controls via relay contacts: a volt-free input is one of the three routes, and a device that only knows on and off may go to the next lower technically possible value. For subsidising a newly installed heat pump under the BEG directive of 17 August 2026, no: under number 3.4.3 it requires a digital, interoperable interface that also delivers status and feedback information. A contact provides no feedback, even if the device then throttles instead of switching off.
The control unit at the meter position that receives the grid operator's signal and passes it on – via volt-free relay contacts or a digital interface. Its requirements are set out in a VDE FNN specification. It belongs to the smart metering system and is provided by the metering point operator, not bought by the system owner.
The statements come from the documents below, each with the date it was checked. Binding in any individual case are the technical connection conditions of the responsible grid operator and the documentation of the specific device at its firmware revision.
This article replaces neither the manufacturer's documentation nor the technical connection conditions of your grid operator. Connecting and registering controllable consuming devices is reserved for a registered electrical contractor.