Section 14a · Existing systems
Section 14a for existing systems
What applies to heat pumps from before 2024, what happens in 2029 and when switching voluntarily pays off.
Read the article →Technical article · Section 14a EnWG · Meter cabinet
The heat pump is ordered, the grid operator wants control under section 14a – and there is no room in the meter cabinet. No APZ panel, no control device panel, the space for additional applications full. This is the most common bottleneck in renovations, and it often only shows up on installation day. This page shows what has to go into the cabinet, how much space it needs and which three ways exist for existing cabinets – according to Netze BW's technical minimum requirements.
Determination BK6-22-300 of the Federal Network Agency clearly places responsibility for the technology on the operator's side. Item 4.6:
“The operator must ensure that the controllable device is equipped with the necessary technical equipment including control devices and is always controllable.”
On top comes a decision the operator must make for each system under item 4.4: direct control, where the individual system receives the setpoint, or control via an energy management system, which distributes one overall setpoint across all connected systems. This choice determines the wiring – with direct control each system needs its own path to the control box, with an EMS only the EMS does.
And finally documentation: under item 7.2 the operator must be able to show that a requirement of the grid operator was implemented, and keep this information for at least two years under item 7.3.
The bottleneck has a number. Netze BW writes in its technical minimum requirements for the control of electrical installations (version 1.0, April 2026):
“When using a smart metering system in three-point design including a control box, the space for additional applications in the modern metering device with 8 modules is undersized. A control device panel, a space for APZ or an additional space for additional applications or a small installation distribution board with at least 10 modules is therefore required.”
In plain terms: the space for additional applications (RfZ) above the meter has eight modules. Smart meter gateway and control box together do not fit. One of four things is needed in addition: a control device panel (SG panel), a space for APZ, an additional space for additional applications (zRfZ) or a small distribution board with at least 10 modules.
For new installations this is solved: under the current VDE-AR-N 4100 in its 2026-04 edition there are new control device panels with a mounting plate and DIN rail. Netze BW requires them to be considered when preparing the meter slot – sealable, with at least one 12-module DIN rail. The real problem is existing installations.
For existing three-point meter slots where the standard solution does not work, Netze BW refers to the BDEW application guide and names three ways in section 6.3, in this order:
“If a distribution panel is present, the lowest DIN rail is to be used as zRfZ.” The same requirements apply to this additional space as to the space for additional applications under VDE-AR-N 4100: an unmetered power supply with socket and a communication line with an RJ-45 socket.
This is the cheapest way if a DIN rail in the distribution panel can be freed up. In many existing cabinets that is exactly the sticking point: the lowest rail is occupied and the devices on it have to move.
If there is no distribution panel or it cannot be converted, “an adapter plate BKE-AZ with at least 12 modules for the space for additional applications can be provided by the installer” on the three-point meter slot. The power supply for the smart meter gateway and control device then comes from the grid-side connection space and has to be prepared in line with VDE-AR-N 4100. In this case the metering operator fits a plug-in meter.
If neither works, the equipment moves out of the cabinet. Netze BW allows a “control device location outside the meter cabinet in its immediate vicinity”. The requirements:
Which way is right is decided on site at the cabinet – but before the installation date. Anyone who only finds out with the heat pump in the basement that way 1 does not work has to replan the conversion. A photo of the open meter cabinet in advance makes the decision possible at the desk.
Between the metering operator's area and the customer's installation there is a defined interface. Netze BW specifies:
With analogue control an electrical detail comes in that is often overlooked in practice: “The contacts of the control devices are rated for a voltage of 5-250 V and a continuous current capacity of 1 A.” If that is not enough for the device's control input, or the logic has to be reversed – normally open instead of normally closed –, coupling relays must be used in the customer installation, for example in the distribution panel. If one signal has to reach several devices, it is multiplied there as well.
Which devices have a suitable interface at all is covered in Does my device meet section 14a EnWG?
| Where | What |
|---|---|
| Space for additional applications → control device panel | data cable at least Cat 5, mandatory if control runs via the control device panel |
| Space for additional applications, APZ, control device panel | power supply required under VDE-AR-N 4100 |
| Additional space in the distribution panel (way 1) | unmetered power supply with socket, communication line with RJ-45 |
| BKE-AZ adapter plate (way 2) | power supply from the grid-side connection space |
| External control device enclosure (way 3) | power supply and data line at least Cat 5 |
Between the meter cabinet and the device or energy management system, the line depends on the interface: a network cable for digital control, a control line for analogue. Other grid operators have their own, sometimes different requirements – the comparison of two grid operators in the guide to section 14a shows how far apart they can be. If the walls are open anyway, lay both.
And a note from my own practice in automation engineering: a conversion like this is drawn beforehand. A clean single-line diagram of the meter cabinet after the conversion is useful not only for registration with the grid operator but for anyone who has to work on the cabinet again in ten years. What such a diagram looks like for a PV system is shown by the sample sheets in the article on the single-line diagram.
According to Netze BW's minimum requirements, the 8-module space for additional applications of a three-point meter slot with a smart metering system and control box is not enough. What is needed is a control device panel, a space for APZ, an additional space for additional applications or a small installation distribution board with at least 10 modules.
Netze BW names three ways: if there is a distribution panel, its lowest DIN rail becomes the additional space for additional applications. Otherwise a BKE-AZ adapter plate with at least 12 modules can go on the three-point meter slot, or a sealable control device enclosure with at least 2 × 12 modules is installed right next to the meter cabinet.
Netze BW always requires an RJ-45 socket as the interface and, if control runs via a control device panel, a data cable of at least Cat 5 between the space for additional applications and the control device panel. For analogue control, a control signal terminal strip is added. Towards the device or energy management system, a network cable or a control line runs depending on the interface; other grid operators have their own requirements.
Yes. Under VDE-AR-N 4100 a power supply is required in the space for additional applications, the APZ space or the control device panel. With the BKE-AZ adapter plate it is prepared from the grid-side connection space, with the additional space for additional applications as an unmetered supply, and with the external control device enclosure as well.
Not necessarily. According to Netze BW, the contacts of the control devices are rated for 5 to 250 V and 1 A continuous current. If that is not enough or the logic has to be inverted, i.e. normally open instead of normally closed, coupling relays must be used in the customer installation, for example in the distribution panel.
All information comes from the following documents, each with the date it was checked. VDE-AR-N 4100 itself is not freely available; where it is mentioned, this is as Netze BW reproduces it in its minimum requirements. All sources are in German.
This article does not replace your grid operator's technical connection conditions. Work in the meter cabinet is reserved for a registered electrical contractor.
Planning the conversion of an existing meter cabinet for a heat pump or wallbox and want to know beforehand which way fits? Write to me – the initial consultation is free.