No other figure in German grid connection law is misread so often. It is not a registration threshold, it is not different in every federal state, and it appears twice in the ruling – meaning different things each time. This page clears up the three most common misconceptions, each with the wording of the source.
This is the root of most misunderstandings. In the federal network agency's ruling, 4.2 kW occurs in two places, and it means something entirely different in each.
As a threshold – above which size an installation falls under the rule at all. Clause 2.4.1 covers heat pumps, charging points, room cooling systems and electricity storage “with a grid connection capacity of more than 4.2 kilowatts (kW) and a direct or indirect connection in the low-voltage grid”.
As a minimum power – how much has to remain when the grid operator intervenes. Clause 4.5.1: “For every controllable consuming device […] controlled pursuant to clause 4.4.a. (direct control), the minimum power is 4.2 kW.”
Both times 4.2 kW, both times something different: once whether the rule applies, once what remains when it does. Confusing the two turns the control into a shutdown – or the threshold into a registration limit. Both are wrong, and both are common.
This is the most frequent false assumption, and it can be expensive. The 4.2 kW decide only whether an installation is controllable within the meaning of section 14a. They say nothing about registration.
The duty to report sits elsewhere, namely in section 19(2) of the low-voltage connection ordinance – and that one sets no general power threshold. Extensions and modifications of installations must be reported, as must additional consuming devices where the capacity to be held available rises or grid perturbations are to be expected. For a heat pump both apply in practice, even at 3 kW.
A genuine approval threshold exists only for charging points: if their combined rated capacity exceeds 12 kVA per electrical installation, the grid operator must consent beforehand. Below that, reporting suffices – but it does not cease to apply.
It does not. All three levels are federal law:
What genuinely differs has nothing to do with state borders and everything with grid operators: they decide how the control is implemented technically and set the level of grid fees. Two neighbouring towns in the same state can therefore face different requirements – and one operator sometimes spans state borders. How different this looks in practice is shown by the comparison of two operators in the guide to section 14a EnWG.
This idea comes up regularly, and the arithmetic even works out: a three-phase connection fused at 6 A yields about 4.15 kW – just under the threshold. Three things nevertheless argue against it.
First, grid connection capacity counts, not the fuse. The ruling refers to the capacity of the installation. A heat pump drawing 6 kW does not become a 4 kW installation because a smaller fuse sits in front of it – it becomes an installation that trips its fuse.
Second, heat pumps and air conditioners are added together. Clause 2.4.2 of the ruling: in the categories heat pump heating and room cooling, where “several installations exist behind one grid connection”, what matters is “whether the sum of the grid connection capacities of all installations exceeds 4.2 kW per category”. Two heat pumps of 3 kW each are above it together. The ruling does not provide for this combination for charging points and battery storage; there each installation counts on its own. And the electric heating element counts towards the heat pump – in refurbishments this is regularly overlooked.
Third, and this weighs heaviest: you don't actually want to be below. Staying under the threshold avoids the control – but also forfeits the reduced grid fee that section 14a brings. And the control being avoided is milder than its reputation: the grid operator reduces to at least 4.2 kW, it does not switch off.
A heat pump sized too small to fit under a legal threshold will not heat the house. Sizing follows the building's heat load, not the wording of a ruling. Anyone forced to choose between the two has a sizing problem – not a legal one.
Where an installation falls under section 14a, the grid operator may temporarily limit its draw in strained grid situations. How far is stated above: to at least 4.2 kW. With several controllable devices under energy-management control this adds up according to a formula set out in clause 4.5.2 – a simultaneity factor enters there, and for heat pumps and cooling systems above 11 kW a scaling factor of 0.4 applied to the grid connection capacity takes the place of the 4.2 kW.
In return the connection user is entitled to a reduction of the grid fee, with a choice between variants. Which one pays off when, what role an energy management system plays and what has to be provided for in the meter cabinet is covered in detail in the guide to section 14a EnWG.
It does. The 4.2 kW only decide whether an installation falls under section 14a EnWG – not whether it has to be reported to the grid operator. That duty is in section 19(2) of the low-voltage connection ordinance (NAV), which sets no general power threshold: any additional consuming device must be reported if the capacity to be held available rises or if grid perturbations are to be expected. For a heat pump that is practically always the case.
Yes. Section 14a is part of federal energy law, its implementation is governed by the nationwide ruling BK6-22-300 of the federal network agency, and the duty to report sits in the low-voltage connection ordinance, also federal law. Differences do not run between federal states but between grid operators – in how the control is implemented technically and in the level of grid fees.
Technically yes, economically rarely sensible. What counts is the grid connection capacity, and several heat pumps or several air conditioners behind one connection are added together – two heat pumps of 3 kW each are jointly above the threshold. The electric heating element counts towards the heat pump. Above all: staying below the threshold forfeits the reduced grid fee that section 14a brings with it.
The installation is reduced to at least 4.2 kW, not switched off. That is the second meaning of the same figure: clause 4.5.1 of the ruling names 4.2 kW as the minimum power that must remain available under direct control. A heat pump keeps running in this state, at reduced output.
Not the Power Dock itself, but what is connected to it. A wallbox on the Power Dock's CEE output, according to Anker for chargers up to 11 kW three-phase, is a private charging point with more than 4.2 kW and falls under section 14a. For the batteries, what counts is the power at which they charge from the grid: Anker states a maximum AC charging power of 1200 W for the Solarbank 3 Pro, so a single unit is well below the threshold. The Power Dock connects up to four of them. Whether four Solarbanks on one Power Dock count as one battery above 4.2 kW is not expressly regulated by the ruling, because its rule on adding installations together only covers heat pumps and air conditioners. The grid operator clarifies this at registration, which is needed anyway: Anker explicitly does not classify the system as a balcony power plant.
All statements come from the documents below, each with the date it was checked. In any individual case the technical connection conditions of the responsible grid operator apply in addition.
This article replaces neither the regulator's ruling nor the technical connection conditions of your grid operator. Registration and connection are reserved for a registered electrical contractor.
Planning a heat pump, wallbox or battery and want control and metering thought through together from the start? Write to me – the initial consultation is free.