Technical article · Grid connection

The single-line diagram for registering a PV system

“Which diagram does the grid operator accept?” is a question that turns up in search queries again and again, and the answer is unsatisfying: there is no form to fill in. What is required is content, not a layout. This page states what that content is and provides five finished sheets for comparison.

Five sample sheets

The drawings below cover the layouts that account for most single-family homes: one or two inverters, with or without storage. They originate from project drawings and have been stripped of every reference to a specific installation or customer for publication; the device label has deliberately been generalised to “Wechselrichter” (inverter) so the sheet works as a template regardless of make. The drawings are in German, which is the language they are submitted in.

Each variant also comes as a fillable version. In it, the details every drawing needs are set up as form fields: in the title block the customer, installation number, date, editor and checker, plus the installation description – and in the equipment boxes room for module output, inverter type and storage capacity. It can be filled in with any PDF viewer that supports forms.

Deliberately not set up as fields are string count and wiring. Changing those means changing the drawing – and that belongs in the CAD system of the electrical contractor doing the work. A sheet that appeared to be fillable in full would invite exactly the mistake the next paragraph warns about.

These are samples, not templates to submit. An overview circuit diagram describes one particular installation, and by submitting it the electrical contractor confirms that it has been built that way. These sheets show the level of detail and the style of representation that are customary – string count, metering concept, meter cabinet and equipment designations have to match your own installation.

Need the diagram for your own system? I draw it from your details – €50 per diagram.

What is required
an overview circuit diagram from the grid connection onwards, drawn single-line
Legal basis
VDE-AR-N 4105, Annex F.1 (application form)
Must contain
every item of equipment from the module to the point of common coupling, plus the metering concept
Additionally above 30 kVA
location of the central grid and system protection, design of the coupling switches
Submission
by the registered electrical contractor
Status
September 2026 · primary sources below, with the date each was checked
Author
Julian Haag, state-certified electrical engineering technician

Why there is no form

Almost every step of the registration has its own template: application, data sheet, commissioning report, declaration of conformity. The overview circuit diagram is the exception – in the forms it appears only as a tick box confirming that it is attached. The governing sentence is in the application form of application rule VDE-AR-N 4105 and reads, in the German original:

“Übersichtsschaltplan ab Netzanschluss beigefügt (inkl. Darstellung des Messkonzeptes und bei Erzeugungsanlagen/Speicher > 30 kVA des Einbauortes des zentralen NA-Schutzes und der Ausführungsvariante der Kuppelschalter, einpolige Darstellung, bspw. Bild 7 aus Anhang B.1.7)” – an overview circuit diagram from the grid connection onwards is attached, including the metering concept, and for generating plants/storage above 30 kVA the installation location of the central grid and system protection and the design variant of the coupling switches, drawn single-line.

Everything else follows from that. “From the grid connection onwards” fixes where the drawing begins – not at the inverter but at the service entry box. “Single-line” means one line per route, not three phase conductors and a neutral drawn separately. And “including the metering concept” is the point at which most submitted diagrams have to be revised.

Netze BW states the same requirement in its own words and is somewhat more explicit about the scope: what is needed is “all system components, technology for grid safety management as well as the installation from the module to the point of common coupling” – and specifically, in the operator's wording, an “updated overview circuit diagram from your electrical contractor”.

What has to be on the sheet

Taken together, the two sources yield a list short enough to walk through before submitting – and short enough that a missing item stands out.

Above 30 kVA of generation or storage capacity two further items apply that are not required below it: the installation location of the central grid and system protection and the design variant of the coupling switches. Below that threshold the protection integrated into the inverter performs this task, and the diagram does not show it separately.

What the samples do not cover

Three cases lie outside what these sheets show, and all three are more common than the drawings suggest.

Other grid operators. What Stromnetz Berlin and EWE Netz require beyond VDE-AR-N 4105 is covered on separate pages: Single-line diagram for Stromnetz Berlin and Single-line diagram for EWE Netz. How Netze BW implements control under section 14a is covered in Section 14a EnWG at Netze BW.

Frequently asked questions

Which diagram does Netze BW accept for a PV system?

An overview circuit diagram starting at the grid connection, drawn single-line, showing every component from the module to the point of common coupling along with the metering concept. There is no fixed form to fill in: what counts is the content, not the layout. It is submitted by the electrical contractor.

Does the diagram have to be drawn in a CAD program?

No. The application rule does not prescribe a tool. What is required is an unambiguous single-line representation using standard symbols and legible equipment designations. A clean hand drawing meets that just as well as an EPLAN sheet — a photo of the installation or a manufacturer's brochure does not.

Do I need a central NA protection device in the drawing?

Only above 30 kVA of generation or storage capacity. In that case the installation location of the central grid and system protection and the design variant of the coupling switches must be shown as well. Below that threshold the protection integrated into the inverter performs this function.

Who is allowed to submit the diagram?

The electrical contractor listed in the grid operator's installer register who connects the system. By submitting the diagram, that company vouches for the installation being built as shown.

A change is coming: the new edition of the application rule

VDE-AR-N 4105 appeared in a revised edition in spring 2026. Netze BW puts the transition period at twelve months from publication – during that time registration under the previous edition remains possible. Little changes for the overview circuit diagram itself; the requirement quoted above is already taken from the new edition. Anyone registering now should agree with their electrical contractor which edition the submission follows, because the certificates to be enclosed depend on it.

Sources

The requirements in this article come from the documents below, each with the date it was checked. In any individual case the technical connection conditions of the responsible grid operator are what binds.

This article replaces neither the application rule nor the technical connection conditions of your grid operator. Registering and connecting a generating plant is reserved for a registered electrical contractor.

Your single-line diagram is still missing? I draw it from your details – €50 per diagram.