Grid connection · Basics
The single-line diagram for registering a PV system
What VDE-AR-N 4105 requires, what Netze BW says about it, and why there is no standard form.
Read the article →Technical article · Grid connection · EWE Netz
EWE Netz requires the single-line diagram (Übersichtsschaltplan) of a PV system at two points: as an upload when registering, and with more detail for commissioning. For the second point, the technical connection conditions contain wording not found in VDE-AR-N 4105: metering, module and inverter assignment per building. This page compiles what EWE Netz requires and shows what a sample sheet still lacks for it.
The basic requirement is in the application form of VDE-AR-N 4105: a single-line diagram “from the grid connection”, including the metering concept. What that means in general is covered in The single-line diagram for registering a PV system. EWE Netz then requires the diagram at two points:
dea.ewe-netz.de). The checklist for it names the
documents to be uploaded in digital form (PDF/JPG) depending on the planned system, among them a single-line
diagram of the electrical installation.The checklist calls the diagram “single-phase” (einphasig). What is meant is the single-line representation that the TAB names elsewhere and VDE-AR-N 4105 requires: one line per circuit.
If the system sits on one roof, the assignment is trivial. It gets interesting once modules sit on several buildings, such as the house and the garage or a barn. Then the diagram has to show for each building which modules are there, which inverter they are connected to and where metering takes place.
The metering concepts EWE Netz asks about are listed in the checklist: full feed-in, surplus feed-in or zero feed-in, the latter only with storage. Which applies determines which meters appear in the diagram.
The five sheets are the same as for every grid operator: one or two inverters, with or without battery, each also as a fillable version. They were derived from project drawings and stripped of all system and customer references.
One inverter, no storage
One module array with two strings, DC surge protection, smart meter and
bidirectional meter. The base case.
One inverter with storage
As above, plus a battery coupled on the DC side of the hybrid
inverter.
Two inverters, no storage
Two separate module arrays – two roof surfaces with different
orientations, say – each on its own inverter.
Two inverters, one battery
Two module arrays, with the battery attached to one of the two
inverters.
Two inverters, two batteries
The largest of the five: two module arrays and two batteries routed to
one inverter.
| Item | In the sample sheet |
|---|---|
| single-line from the grid connection, metering concept | yes, surplus feed-in with bidirectional meter and smart meter |
| module assignment to the inverter | yes, module arrays drawn per inverter |
| assignment per building | no; with several buildings, add the building boundaries and the arrays per building |
| module and inverter data | fields for module power and inverter type in the fillable version |
| full or zero feed-in | no, the samples show surplus feed-in |
These are samples, not templates for submission. A single-line diagram describes one specific system, and by submitting it the electrical contractor confirms that it was built that way. Strings, metering concept and meter panel must match your own system.
Need the diagram for your own system in the EWE grid, including several buildings? I draw it from your details – 50 € per diagram.
Besides the single-line diagram, the checklist names, depending on the system:
It also asks for the metering concept and the expected generation and self-consumption, and the installer must be registered in the installer directory.
In its supplements to the TAB, EWE Netz writes: before every commissioning, the required documents including the completion notice have to be submitted via the customer marketplace. Generating units and storage may, from a total power above 30 kW per property including existing systems, only be commissioned in the presence of an EWE Netz employee. Below that, the installer commissions the system on their own responsibility and reports it without delay via the customer marketplace.
Above 30 kVA, VDE-AR-N 4105 also requires the location of the central grid and system protection and the design of the coupling switches in the diagram.
For registration in the feed-in registration portal, according to the checklist, a single-line diagram of the electrical installation as PDF or JPG. For commissioning, the TAB NS Nord 2023 applied by EWE Netz names, for PV systems, a single-line diagram with metering and module and inverter assignment per building. The basic requirement from VDE-AR-N 4105 applies as well: single-line, from the grid connection, with the metering concept.
If the PV system sits on several buildings, for example the house and the garage, the diagram has to show for each building which modules are there and which inverter they are connected to. The metering belongs with it, i.e. where which meter sits. The wording comes from Annex B of the TAB NS Nord 2023.
According to EWE Netz's supplements to the TAB, up to a total power of 30 kW per property, existing systems included. Above that, generating units and storage may only be commissioned in the presence of an EWE Netz employee. Before every commissioning the documents including the completion notice have to be submitted via the customer marketplace.
The requirements in this article come from the following documents, each with the date it was checked. In the individual case, EWE Netz's technical connection conditions in their current version are binding.
This article replaces neither the application rule nor EWE Netz's technical connection conditions. Registering and connecting a generating unit is reserved for a registered electrical contractor. Haag Automation has no business relationship with EWE Netz.