Technical article · Grid connection · EWE Netz

Single-line diagram for EWE Netz

EWE Netz requires the single-line diagram (Übersichtsschaltplan) of a PV system at two points: as an upload when registering, and with more detail for commissioning. For the second point, the technical connection conditions contain wording not found in VDE-AR-N 4105: metering, module and inverter assignment per building. This page compiles what EWE Netz requires and shows what a sample sheet still lacks for it.

Basis
TAB low voltage EWE Netz, status 08/2024 (TAB NS Nord 2023 v2.0 with supplements), checklist for online registration, both German
Registration
feed-in registration portal, upload as PDF or JPG
Commissioning
diagram with metering, module and inverter assignment per building
Above 30 kW
commissioning only with an EWE employee present
Status
October 2026 · primary sources below, with the date each was checked
Author
Julian Haag, state-certified electrical engineering technician

What EWE Netz requires

The basic requirement is in the application form of VDE-AR-N 4105: a single-line diagram “from the grid connection”, including the metering concept. What that means in general is covered in The single-line diagram for registering a PV system. EWE Netz then requires the diagram at two points:

  1. At registration. According to EWE Netz's supplements to the TAB, generating units and storage are registered via the feed-in registration portal (dea.ewe-netz.de). The checklist for it names the documents to be uploaded in digital form (PDF/JPG) depending on the planned system, among them a single-line diagram of the electrical installation.
  2. At commissioning. Annex B of the TAB NS Nord 2023, which EWE Netz applies, lists the documents for the commissioning process. For PV systems, the column “information on design and operation” reads (translated): “single-line diagram with metering, module and inverter assignment per building”. If the installed system differs from the registration, the complete documents have to be resubmitted with the commissioning notice at the latest.

The checklist calls the diagram “single-phase” (einphasig). What is meant is the single-line representation that the TAB names elsewhere and VDE-AR-N 4105 requires: one line per circuit.

“Per building”: what it means in the diagram

If the system sits on one roof, the assignment is trivial. It gets interesting once modules sit on several buildings, such as the house and the garage or a barn. Then the diagram has to show for each building which modules are there, which inverter they are connected to and where metering takes place.

Module and inverter assignment per building Two buildings side by side. On the house is module array 1, connected to inverter 1. On the garage is module array 2, connected to inverter 2. Both inverters lead to the meter panel in the house with the metering, and from there to the service connection. The diagram shows for each building which modules are connected to which inverter. Building 1: house Module array 1 number · power Inverter 1 Building 2: garage Module array 2 number · power Inverter 2 Meter panel with metering surplus, full or zero feed-in Service connection
Example with two buildings on one property. The requirement “metering, module and inverter assignment per building” comes from Annex B of the TAB NS Nord 2023; the split into house and garage is only an example.

The metering concepts EWE Netz asks about are listed in the checklist: full feed-in, surplus feed-in or zero feed-in, the latter only with storage. Which applies determines which meters appear in the diagram.

Five sample sheets and what EWE Netz adds

The five sheets are the same as for every grid operator: one or two inverters, with or without battery, each also as a fillable version. They were derived from project drawings and stripped of all system and customer references.

Sample sheets against EWE Netz's requirements
ItemIn the sample sheet
single-line from the grid connection, metering conceptyes, surplus feed-in with bidirectional meter and smart meter
module assignment to the inverteryes, module arrays drawn per inverter
assignment per buildingno; with several buildings, add the building boundaries and the arrays per building
module and inverter datafields for module power and inverter type in the fillable version
full or zero feed-inno, the samples show surplus feed-in

These are samples, not templates for submission. A single-line diagram describes one specific system, and by submitting it the electrical contractor confirms that it was built that way. Strings, metering concept and meter panel must match your own system.

Need the diagram for your own system in the EWE grid, including several buildings? I draw it from your details – 50 € per diagram.

What else is uploaded

Besides the single-line diagram, the checklist names, depending on the system:

It also asks for the metering concept and the expected generation and self-consumption, and the installer must be registered in the installer directory.

Commissioning: the 30 kW limit

In its supplements to the TAB, EWE Netz writes: before every commissioning, the required documents including the completion notice have to be submitted via the customer marketplace. Generating units and storage may, from a total power above 30 kW per property including existing systems, only be commissioned in the presence of an EWE Netz employee. Below that, the installer commissions the system on their own responsibility and reports it without delay via the customer marketplace.

Above 30 kVA, VDE-AR-N 4105 also requires the location of the central grid and system protection and the design of the coupling switches in the diagram.

Frequently asked questions

Which single-line diagram does EWE Netz require for a PV system?

For registration in the feed-in registration portal, according to the checklist, a single-line diagram of the electrical installation as PDF or JPG. For commissioning, the TAB NS Nord 2023 applied by EWE Netz names, for PV systems, a single-line diagram with metering and module and inverter assignment per building. The basic requirement from VDE-AR-N 4105 applies as well: single-line, from the grid connection, with the metering concept.

What does “module and inverter assignment per building” mean?

If the PV system sits on several buildings, for example the house and the garage, the diagram has to show for each building which modules are there and which inverter they are connected to. The metering belongs with it, i.e. where which meter sits. The wording comes from Annex B of the TAB NS Nord 2023.

May the electrician commission a PV system at EWE Netz without the grid operator?

According to EWE Netz's supplements to the TAB, up to a total power of 30 kW per property, existing systems included. Above that, generating units and storage may only be commissioned in the presence of an EWE Netz employee. Before every commissioning the documents including the completion notice have to be submitted via the customer marketplace.

Sources

The requirements in this article come from the following documents, each with the date it was checked. In the individual case, EWE Netz's technical connection conditions in their current version are binding.

This article replaces neither the application rule nor EWE Netz's technical connection conditions. Registering and connecting a generating unit is reserved for a registered electrical contractor. Haag Automation has no business relationship with EWE Netz.

Still missing your single-line diagram for EWE Netz? I draw it from your details – 50 € per diagram.