Photovoltaics · EEG 2027
Germany's feed-in tariff in 2026 and 2027
5.2 cents for three years instead of 7.70 cents for twenty: what the bill says and what applies until 31 December.
Read the article →Technical article · Photovoltaics · Registration
Every grid-connected solar system in Germany belongs in the Federal Network Agency's market master data register (Marktstammdatenregister, MaStR) – the rooftop system, the battery and the balcony unit as well. The deadline is short: one month after commissioning. Miss it and you pay per kilowatt and month. This page explains who has to register what, how registration works step by step, and what forgetting it costs – each with the wording of the ordinance.
The duty is laid down in § 5(1) of the Market Master Data Register Ordinance (MaStRV):
“Operators must register their units, their EEG and CHP installations in the market master data register.”
The sentence is short, and it covers everyone operating a solar system. Under paragraph 2 the only exceptions are generators and storage units that are “neither directly nor indirectly connected to a power grid or intended to be connected to one” – true off-grid systems, such as on a garden shed without a grid connection. Everything else goes into the register:
The operator must also register themselves as a “market actor” (§ 3 MaStRV). In the simplified procedure for private individuals this happens in the same form as the registration of the system.
§ 5(5) MaStRV: registrations “must take place within one month of commissioning in the case of units and EEG installations”. Two consequences that are often misunderstood:
The same one-month deadline applies to changes: if a battery is added, the system is extended or the operator changes, this must be in the register “within one month of its occurrence” (§ 7(1) MaStRV).
For private individuals there is a simplified registration wizard – for balcony units and for rooftop solar systems. The procedure according to the Federal Network Agency's handbook (the portal is in German; the button labels are given in the original):
noreply@marktstammdatenregister.de – and, according to the handbook,
sometimes lands in the spam folder.Have ready what the form asks for: the commissioning date (from the electrician's report), the capacity of the modules and the inverter, the orientation for a rooftop system, and the battery data. The handbook explicitly recommends “looking up the data on the system and having it to hand”.
For a balcony unit the form checks the limits of 2,000 watts module capacity and 800 watts inverter capacity. If the system exceeds them, it suggests switching to the rooftop wizard. Besides personal details, a balcony unit now needs only five entries; before 1 April 2024 it was around twenty.
The consequence is not in the register ordinance but in the EEG. Under § 52(1) no. 11 an operator must pay their grid operator if they have not submitted the data required for registration “and no report under § 71(1) no. 1 has been made” – that is the annual data report to the grid operator.
| Situation | per kW and month | 10 kW system |
|---|---|---|
| Registration missing | €10 | €100 per month |
| Registration completed – retroactively for the whole period | €2 | €20 per month |
The reduction to €2 applies “as soon as the relevant duty is fulfilled” and “takes effect retroactively to the beginning of the breach”. Registering half a year late therefore costs €120 for 10 kW – not registering at all costs €100 every month. Catching up always pays, and immediately.
A missed registration is also an administrative offence (§ 21 MaStRV in conjunction with § 95 EnWG). The statutory range goes up to €50,000; for a private rooftop system that is a theoretical maximum, not a usual order of magnitude. The payment under § 52 EEG is the consequence that actually occurs.
The Marktstammdatenregister is not the notification to the grid operator. The two run separately:
Within one month of commissioning, as set out in § 5(5) of the Market Master Data Register Ordinance. Not before: systems still being planned are only registered after commissioning. If your system is commissioned on 20 December, you have until 20 January.
Yes. The duty only lapses for installations that are neither directly nor indirectly connected to a power grid. A balcony solar unit plugged into a socket is connected. Since 1 April 2024 there is a simplified registration: besides personal details, only five entries about the unit are needed.
Yes, a battery is a separate unit with its own registration duty. In the simplified form it can be entered together with the solar system: answer yes to the question about a storage unit, and the fields for its technical data appear. A battery added later is registered within one month of its own commissioning.
Under § 52 EEG the operator must pay the grid operator €10 per kilowatt of installed capacity and month for as long as registration is missing and the annual data under § 71 EEG has not been reported either. Once registration is completed, the amount falls retroactively to €2 per kilowatt and month. For a 10 kW system that is €100 or €20 per month respectively.
No, these are two separate procedures. Notifying the grid operator covers the grid connection and, for a rooftop system, is handled by the electrician. Registration in the Marktstammdatenregister is a separate duty of the operator towards the Federal Network Agency.
All information comes from the following documents, each with the date it was checked. All sources are in German.
This article is not legal advice. The ordinance and the notes in the Federal Network Agency's registration wizard are authoritative.
Planning a PV system with a battery and want registration, metering and control thought through together from the start? Write to me – the initial consultation is free.