Technical article · Funding · Section 14a EnWG

KfW heat pump subsidy when the control box is still missing

The heat pump is running, KfW wants the proof, and the grid operator will not fit the control box for another year. Do you have to wait, and do you lose the grant otherwise? The answer depends on when the application was filed. Since July 2026 there are two versions of the funding guideline, and they require different things. Neither requires the control box to be installed. This page sets both versions side by side, with the wording of the sources. The sources are German; quotations are our translation.

Applies to
KfW grant for replacing a heating system (programme 458, private individuals) under the BEG EM funding guideline
Application up to 20.07.2026
BEG EM of 21 December 2023: interface for grid-serving activation, for example SG Ready
Application from 21.07.2026
BEG EM of 17 August 2026: digital interface with feedback, smart metering system requested
Control box installed?
required in neither version
Status
23 October 2026 · primary sources below, with the date each was checked
Author
Julian Haag, state-certified electrical engineering technician

The essentials in one minute

Which version applies: the application date decides

The funding guideline for the Federal Funding for Efficient Buildings – Individual Measures (BEG EM) was rewritten in 2026. The version of 17 August 2026, published in the Federal Gazette on 27 August, takes effect “as of 21 July 2026” and replaces the version of 21 December 2023. For older applications, number 10 provides:

“For funding applications filed before this funding guideline entered into force, the last version of the replaced funding guideline applies, even if the decision on the application is only made after this funding guideline entered into force.”

So it is not the installation, commissioning or approval date that counts, but the date the application was filed. Anyone who applied in 2024 or 2025 and installs in 2026 falls under the 2023 version. The date is in the KfW approval.

Before publication in the Federal Gazette, energiewechsel.de carried a version dated “17 July 2026”. At the passages quoted here (number 10 and number 3.4.3 of the technical minimum requirements) its wording is identical.

Which controllability requirement applies to which application At the top the question of when the KfW application was filed. Left branch: application up to 20 July 2026, the BEG EM of 21 December 2023 applies; required is an interface for grid-serving activation, for example SG Ready or VHP Ready, from 2025 connectable to a smart meter gateway, proven by a manufacturer's declaration. Right branch: application from 21 July 2026, the BEG EM of 17 August 2026 applies; required are a digital interface with feedback, a requested installation of a smart metering system with control device and confirmation at commissioning that the interface is activated. At the bottom across both branches: neither version requires the control box to be installed already. When was the KfW application filed? up to 20.07.2026 BEG EM of 21.12.2023 interface for grid-serving activation, e.g. SG Ready, VHP Ready from 2025: SMGW connectable proof: manufacturer's declaration from 21.07.2026 BEG EM of 17.08.2026 digital interface with feedback smart meter with control box requested at commissioning: interface activated from 07/2027: format e.g. EEBUS Control box already installed? Required in neither version.
The controllability requirements under number 3.4.3 of the technical minimum requirements, by application date. The wording of both versions is in the sections below.

Applications up to 20 July 2026: the interface is enough

The version of 21 December 2023 covers controllability in the technical minimum requirements under number 3.4.3 “grid serviceability”:

“Eligible heat pumps must have interfaces through which they can be activated and operated automatically in a grid-serving way (for example using the ‘SG Ready’ or ‘VHP Ready’ standards). It is recommended that heat pumps can be connected to a certified smart meter gateway, so that metering and control operations relevant to the energy industry can be handled via a smart meter gateway in line with the requirements of the Energy Industry Act and the Metering Point Operation Act. From 1 January 2025, only heat pumps that meet this requirement will be funded.”

Two phrases carry the answer: “must have” and “can be connected”. What is required is a property of the device. That a grid operator is already controlling it, or that a control box sits in the meter cabinet, is not stated. As proof, number 3.4.7 names the “manufacturer's declaration under BEG EM TMA number 3.4.3 (grid serviceability)”.

What counts as a sufficient interface is listed in the technical FAQ of BAFA and KfW under number 8.23. Grid-serving controllability “is deemed met without further proof for eligible heat pumps” if the heat pump offers at least one of the following:

An SG Ready interface is therefore enough, as is an EEBus module. The stricter obligations of the new version do not apply to these applications: no feedback information, no obligation to order a smart metering system, no confirmation at commissioning. Whether a specific unit counts as grid-serving is also shown in the list of eligible heat pumps: according to the guideline, heat pumps “that have interfaces for grid-serving activation ex works” are “marked accordingly” there.

The technical FAQ apply in the version current at the time of application. According to the version table, number 8.23 was last changed in version 6.0 of 1 June 2024. Applications filed between January and May 2024 fell under version 5.0. Regardless of that, the wording of the guideline itself names SG Ready as an example.

Applications from 21 July 2026: digital and requested

The new version renamed number 3.4.3 “grid and system serviceability” and tightened it considerably:

“Newly installed heat pumps must have a digital interface for grid-oriented control and for connection to a smart metering system including control device. The digital interface must be interoperable and enable grid-oriented control under section 14a of the Energy Industry Act (EnWG), including the status and feedback information required for this.”

A switching contact such as SG Ready reports nothing back and is therefore no longer sufficient. From 1 July 2027, the interface of newly installed heat pumps must also follow a format in line with the European Commission's Code of Conduct for Energy Smart Appliances, “for example EEBUS according to VDE-AR-E 2829-6”.

New is the ordering obligation: after commissioning, the applicant must “request the installation of a smart metering system (iMSys) including control device from the default or a competitive metering point operator”, unless the connection already has one. The list of proofs adds two confirmations:

Here too: requested, activated, connectable. The new version does not require the metering point operator to have installed and connected the control box either. Anyone whose grid or metering point operator cannot come until after the KfW deadline needs the written acknowledgement of their order.

Which route to the heat pump meets this requirement is compared in Running a heat pump on electricity prices.

Number 3.4.3 of the technical minimum requirements in both versions
Application up to 20.07.2026Application from 21.07.2026
GuidelineBEG EM of 21.12.2023BEG EM of 17.08.2026
Interfacegrid-serving activation, e.g. SG Ready or VHP Readydigital, interoperable, with status and feedback information
Smart meter gatewayfrom 01.01.2025: connectableconnection to iMSys with control device, directly or via energy management
Order smart meternot requiredrequest after commissioning, have receipt confirmed
At commissioningno separate confirmationconfirmation: interface operational, activated, connectable
Control box installednot requirednot required
Proofmanufacturer's declarationmanufacturer's declaration and both confirmations

KfW deadlines

The deadlines are the same in both versions. The KfW information sheet on grant 458 sums them up like this:

“You must have fully completed the project within 36 months of the KfW approval (approval period). Within six months of completing the project (date of the last invoice), but no later than six months after the end of the approval period, the proof of implementation must be submitted in the ‘Meine KfW’ customer portal.”

And further: “If you do not meet this deadline, the grant lapses and cannot be paid out.” The period starts with the last invoice, not with the control box. Compliance with the minimum requirements is confirmed by the installer or the energy efficiency expert in the “confirmation after implementation” (BnD). Only then are the proofs submitted in “Meine KfW”.

Holding back the proofs until the grid operator has fitted the control box gains nothing but puts the deadline at risk. Get the manufacturer's declaration on grid serviceability early, and for new applications also the metering point operator's acknowledgement.

Section 14a while the control box is missing

Alongside the subsidy there is the obligation under section 14a EnWG: a heat pump with a grid connection capacity above 4.2 kW that went into operation from 2024 onwards must be controllable by the grid operator. For the time until the grid operator installs the control technology, the Federal Network Agency writes on its consumer page:

“Even if the control technology is only installed later on the grid operator's instruction, you receive the grid fee reduction for grid-oriented control straight away.”

The condition is that you have commissioned the installation, from the metering point operator or the grid operator. And: “As long as the order has not yet been carried out, you cannot be accused of a breach of the controllability obligation in this respect.”

If the grid operator itself is not ready yet, determination BK6-22-300 gives it a transitional solution. Under item 10.5 it may use preventive control until 31 December 2028 at the latest, for no more than 24 months per grid area, “limited to two hours a day” and with the same minimum power as otherwise. It has to announce the start in text form beforehand (item 8.2 b). Where the 4.2 kW minimum comes from: The 4.2 kW in section 14a EnWG.

Example: heat pump with SG1 and an EEBus module

A situation that comes up a lot right now: the funding application was filed before July 2026, the heat pump has since been installed, and the grid operator only announces the control box for a date after the KfW deadline for the proofs. As the unit we take a Bosch air-to-water heat pump with the UI 800 control panel, such as a Compress CS 5800i or CS 6800i AW.

Software versions, modules and wiring in detail: Bosch, Buderus and section 14a EnWG.

Frequently asked questions

Does the control box have to be installed before I submit the proof to KfW?

Not according to the wording of the funding guideline, in neither version. For applications up to 20 July 2026, the heat pump must have the interface and be capable of connection to a smart meter gateway. For applications from 21 July 2026, installation of the smart metering system with control device must have been requested, and the digital interface must be operational, activated and connectable at commissioning. Neither version asks whether the control box is already installed.

Which version of the funding guideline applies to my application?

The date of the application decides. The new guideline took effect on 21 July 2026. For applications filed before that, its number 10 says the last version of the replaced guideline applies, that is the BEG EM of 21 December 2023, even if the decision on the application came later.

Is SG Ready enough for the subsidy?

For applications up to 20 July 2026, yes: the version of 21 December 2023 names SG Ready explicitly as an example, and the technical FAQ on the BEG accept the requirements of point 2.1 of the SG Ready regulations without further proof. For applications from 21 July 2026, no: a digital, interoperable interface with status and feedback information is then required, and a switching contact provides no feedback.

Do I get the reduced grid fee while the control box is missing?

Yes, if you have commissioned the installation. The Federal Network Agency writes that even if the control technology is installed later on the grid operator's instruction, you receive the grid fee reduction for grid-oriented control straight away. You can commission the metering point operator or the grid operator.

Sources

All quotations are translated from the documents below. The guideline PDFs were extracted with pdftotext and checked against the quoted passages.

This article explains the wording of the funding guideline and the determination; it is not funding or legal advice. Whether a project is funded and a proof accepted is decided by KfW. If in doubt, ask KfW quoting your application number and application date, and have your installer or energy efficiency expert prepare the confirmation after implementation.

Want to connect your heat pump so that funding, control box and energy management fit together? Write to me – the initial consultation is free.