Weld twelve metres, or unroll five hundred

When a heat network is built, the pipe material decides more than the cost of the material: the width of the trench, how long the site stays open, how many trades are involved – and whether a leak can later be located electrically.

Example
Ilsfeld heat network, Germany; material change from 2020
Before
steel pipe in lengths of at most twelve metres
After
flexible plastic line, coils of up to 500 metres
Author
Julian Haag, state-certified electrical engineering technician

The difference starts in the trench

A district heating pipe always has three layers: the service pipe carrying the water, an insulation layer around it and an outer protective jacket. What differs between designs is the material of the service pipe – and that has consequences right through to the construction sequence.

In the classic rigid pre-insulated pipe the service pipe is steel. Steel cannot be bent or coiled; it arrives in straight lengths, in this case a maximum of twelve metres. Those lengths have to be welded together in the trench.

The trench profile follows directly from that: every twelve metres the trench has to be widened so a welder can climb in and work. On top of that come the joint works at every connection – making good the insulation, closing the jacket, testing for tightness.

With a flexible line the service pipe is plastic. In this case two pipes of reinforced polyethylene, for flow and return, sit inside a shared flexible insulating jacket. That can be coiled, cut to any length required and laid in one go.

Trench profile for steel pipe and for flexible line With steel pipe the trench must be widened every twelve metres for a welded joint, producing a regular pattern of widenings. With a flexible line the pipe is laid in one run from the coil and the trench keeps the same narrow width along its whole length. Steel pipe: a welded joint every twelve metres widening for welding Flexible line: continuous, from the coil no joints Narrower, uniform trench; less excavation, less backfill, shorter build time. In return: limited diameters, limited temperature and limited pressure.
Own schematic drawing. The widenings are exaggerated.

Why this switch has only recently become possible

The idea of laying heat pipes from a coil is not new. What is new is that the plastics can withstand the operating conditions of a real heat network.

In this case the reasoning is stated explicitly: steel was used in the early years because there were no plastic pipes able to withstand 90 °C and six bar. Only when a manufacturer offered a product that could do both was the switch made.

Those two figures are the heart of the matter. An existing network with radiator heating runs flow temperatures around 80 °C, and the pumps have to build enough pressure to push water through several kilometres of pipe. Exceed the temperature limit with plastic and service life drops sharply – plastics age under heat, and disproportionately so.

What the switch delivers in practice

The advantages are all connected:

Steel pipe and flexible line compared
FeatureSteel in a pre-insulated pipeFlexible plastic line
Supplied asstraight lengths, max. 12 m herecoils of up to 500 m
Jointsweld plus sleeve every 12 monly at branches and service connections
Trench profileregular widenings requireduniformly narrow throughout
Trades involvedcivils, pipe fitting, certified weldercivils for the trench, laying possible by a heating contractor
Lead time in this case—four days
Range of use herestill above 50 mm diameterbelow that

What matters most in practice is not the material price. In this case the plastic pipes are described as "somewhat cheaper" – that alone would not justify a change. The decisive factor is build time: the pipes go in faster, the site stands outside people's front doors for less time, and anyone deciding at short notice to connect need not wait weeks for material.

There is also an organisational advantage that is easily overlooked: laying no longer requires a certified welder. In this case the municipality lays the lines itself with a local heating contractor and only brings in the civil engineering firm for the excavation. Not having to plan a construction stage around the availability of a specialist trade makes an operator considerably more agile.

Where steel stays – and why

The switch is not across the board. Here it applies expressly to the smaller dimensions only: pipes above 50 millimetres in diameter remain metal.

That is not arbitrary but follows from the physics of the materials. Forces on the pipe wall rise with diameter, and plastic would need ever thicker walls to carry them – until the pipe is neither coilable nor affordable. Then there is expansion: plastic moves more than steel under temperature changes, which is harder to control at large cross-sections and over long routes.

So the typical split today looks like this:

A real network is therefore almost always a mixed network – and that is the normal case, not the exception.

The catch worth knowing: leak monitoring

This deserves a closer look, because it connects directly to another subject.

Rigid pre-insulated pipes have monitoring wires embedded in the insulation. If moisture enters, the electrical resistance between those wires and the steel pipe changes, and a travel-time measurement locates the fault to within a few metres. This technique is the reason leaks in district heating mains can be found at all without opening the street on suspicion.

With flexible lines such monitoring is not a given. Versions with monitoring wires exist, but they are not the standard, and a plastic service pipe does not offer the measurement the same reference conductor a steel pipe does.

From that follows a question that ought to be asked alongside the material decision and easily gets lost in the discussion about build time and cost: how will a leak in this section be found later? Where there is no electrical monitoring, only the laborious methods remain – gas detection, thermography, ground microphone – and all of them have blind spots. How arduous that can become is shown by the case of a network losing 650 litres a day without the spot being found.

This is not an argument against flexible pipes. It is an argument for deciding the question deliberately rather than leaving it to the product catalogue.

What this means for expanding a network

The material change alters the economics of network expansion at a decisive point. As long as every metre of route was expensive and slow, a construction stage had to be large enough to be worth it – and anyone deciding too late had to wait for the next round.

With a four-day lead time and laying that needs no specialist trade, short-notice connection requests can be picked up along the way. For a heat network that matters more than it sounds: as described in the article on wastewater heat, it is not the length of a network that decides its efficiency but the heat density per metre of route. Every additional customer on an existing line improves the balance – and the easier a connection is to add later, the more likely it is to happen.

Frequently asked questions

What is a district heating pipe made of?

Three layers: the service pipe carrying the water, an insulation layer around it and an outer protective jacket. The service pipe is either steel or – in flexible lines – plastic, usually polyethylene.

Why were only steel pipes used in the past?

Because no plastic pipes could withstand the operating conditions. In the network considered here those were 90 °C and six bar. Only when products became available that could take both was a switch possible.

What do flexible pipes save?

Above all build time. Steel pipes come in lengths of a few metres and must be welded in the trench, which requires the trench to be widened regularly. Flexible lines come from a coil of up to 500 metres and are laid in one run. The material itself is only somewhat cheaper.

Are steel pipes no longer used at all?

They are. In the network considered here, pipes above 50 millimetres in diameter remain metal. As cross-section grows, forces on the pipe wall increase and thermal expansion becomes harder to control, which is why main lines are almost always steel.

Can leaks in plastic lines be located as in steel pipes?

Not readily. Rigid steel pre-insulated pipes have monitoring wires in the insulation that allow a fault to be located electrically to within a few metres. With flexible lines such monitoring is not the norm; then only more laborious methods remain, such as gas detection, thermography or a ground microphone.

Sources

The details of the material change – supplied lengths, the temperature and pressure limits, the 50-millimetre threshold, lead time and construction sequence – come from a report in the Heilbronner Stimme of 9 September 2020, which the municipality of Ilsfeld makes available on its own heat network pages. The explanation of pipe construction, thermal expansion and leak monitoring is our own. The source documents are in German.