Technical article · Photovoltaics · EEG 2027

Germany's feed-in tariff in 2026 and 2027: the end for new solar

The German government wants to abolish the fixed feed-in tariff (Einspeisevergütung) for new PV installations. Instead of 7.70 cents for 20 years, from 2027 there would be 5.2 cents for three years, and no fixed tariff after that. Anything commissioned by 31 December 2026 keeps the old terms. This page shows what the bill actually says, what is still open, and what it means for a system you are planning now – with the wording of the sources.

Status
government bill, printed paper 21/7867 – not yet passed
Cut-off
commissioned by 31 Dec 2026: old tariff, 20 years
Today (up to 10 kW)
7.70 ct/kWh for surplus export
From 2027
5.2 ct/kWh transitional payment, at most 36 months
Existing systems
unchanged
Status date
30 September 2026 · primary sources below, with the date each was checked
Author
Julian Haag, state-certified electrical engineering technician

The essentials in one minute

Where the bill stands

The official title is Entwurf eines Gesetzes für einen planbaren, kosteneffizienten, netzverträglichen und marktorientierten Ausbau der erneuerbaren Energien im Stromsektor (a bill for a plannable, cost-efficient, grid-compatible and market-oriented expansion of renewables in the power sector), Bundestag printed paper 21/7867 of 7 September 2026. The summary states the goal plainly:

“To this end, the fixed feed-in tariff for new installations will be consistently abolished. This goes hand in hand with a comprehensive obligation for new installations to use direct marketing.”

And on small rooftop systems:

“Support for new installations with less than 25 kilowatts of installed capacity will largely be discontinued.”

The legislative timeline
DateStep
07.09.2026Government bill published as printed paper 21/7867
24.09.2026First reading in the Bundestag, referral to the Committee on Economic Affairs and Energy
05.10.2026Public hearing in committee
openSecond and third reading, Bundesrat
01.01.2027Intended entry into force (Article 7 of the bill)

The same hearing also covers counter-proposals: a motion by the Greens, one by the Left Party calling for no cuts, and a bill by the AfD to abolish the EEG altogether. How the final text will look is therefore open. This page describes the bill as it stands and will be updated as soon as anything changes.

A side note from the Federal Network Agency shows why time matters: the current tariff rates are based on the EEG 2023, “which is applicable until 31 December 2026. A successor regulation for the period after 31 December 2026 is currently under parliamentary deliberation.” The end of the year is a boundary either way, not only in the bill.

Feed-in tariff 2026: the rates until 31 December

If your system is commissioned this year, you get the rates the Federal Network Agency has published for commissioning from 1 August to 31 December 2026 – for 20 years, extended to the end of the twentieth calendar year.

Feed-in tariff for installations on buildings, commissioned 01.08.–31.12.2026
Share of capacitySurplus exportFull export
up to 10 kW7.70 ct/kWh12.22 ct/kWh
over 10 to 40 kW6.66 ct/kWh10.24 ct/kWh
over 40 to 100 kW5.44 ct/kWh10.24 ct/kWh

For a 15 kW system, the first rate applies to the first 10 kW and the second to the rest; the grid operator calculates a blended rate. Most rooftop systems run on surplus export: the house uses the power first, only the remainder goes to the grid. What a rooftop system produces per year at its location, and what that saves on the power bill, is worked out by the solar panel output calculator on xmoo.app.

What “commissioned” means

This decides whether a system still falls under the old rules in December. Section 3 no. 30 EEG defines commissioning as

“the first operation of the installation exclusively with renewable energy […] after it has been made technically ready for operation; technical readiness requires that the installation has been permanently installed at the location intended for permanent operation and permanently fitted with the equipment necessary to generate alternating current”.

In plain terms: modules fixed on the roof, inverter permanently mounted and connected, and the system has produced power for the first time. Modules sitting on a pallet in the yard in December do not count. Neither does an inverter that is only delivered in January.

Check with your grid operator beforehand how they want the date documented, and get a dated commissioning report from your electrician. The system must also be registered within one month in the Federal Network Agency's market master data register (Marktstammdatenregister). If you are only now collecting quotes, get the commissioning date confirmed in writing.

Feed-in tariff 2027: what is to apply to new installations

The bill replaces the feed-in tariff with three ways of disposing of exported power. Which one is available depends on size and year of commissioning.

1. The time-limited transitional payment

It is what remains of the feed-in tariff and, according to the explanatory memorandum, works “along the lines of the previous feed-in tariff”: the grid operator takes the power and pays a fixed rate. The rate is derived from the new uniform reference value of 6.2 cents, from which, under section 53 of the bill, “1 cent per kilowatt-hour is to be deducted” – i.e. 5.2 ct/kWh. From 1 August 2027 the reference value for newly commissioned systems falls by 1 percent every six months.

It is paid “until the 36th calendar month following commissioning”. The Bundestag sums it up itself: instead of 20 years as before, support is to run for only three years.

Who gets the transitional payment (bill, § 21(1) sentence 1 no. 1)
CommissionedInstalled capacity
in 2027below 50 kW
in 2028below 25 kW
in 2029 and 2030below 7 kW
from 2031no transitional payment

The Federal Network Agency may extend this phase until the end of 2032 at the latest if direct marketing for small installations cannot be handled with reasonable effort by then. Balcony solar units are excluded (up to 2 kW module and 800 VA inverter capacity): the bill provides no transitional payment for them, because the billing effort would exceed the value of the few kilowatt-hours they export.

2. Direct marketing with a start-up bonus

After the three years – or from the start – the operator can sell the power on the exchange via a direct marketer. For installations below 25 kW, section 50c of the bill adds a bonus of 1.5 cents per kilowatt-hour exported, for at most 48 months. It is meant to cover the costs of entering direct marketing. On top comes whatever the marketer earns on the market, minus their fee.

What direct marketers will charge for a 10 kW system nobody knows today: there is hardly a market for it yet, which is exactly why the legislator builds in the transition period. No serious figure can be given here yet.

3. Free handover or zero export

If you do not want to deal with marketing, installations below 100 kW can hand their power to the grid operator free of charge. Or they do not export at all: the bill explicitly reduces “hurdles for so-called zero-export installations”, i.e. systems that store or curtail their surplus. Several technical requirements of section 9 are to be waived for them; they must still be registered in the market master data register.

For exported power from new installations below 25 kW that is not directly marketed, the limit of 60 percent of installed capacity at the grid connection also remains in place until a smart meter with a control unit is installed – the same rule that the solar peak law introduced in 2025.

The numbers: build in 2026 or 2027?

Suppose your system exports 1,000 kWh a year – a realistic order of magnitude for a small rooftop system with high self-consumption, and considerably more for many. The amounts scale linearly; insert your own figure.

Revenue for 1,000 kWh exported per year, system up to 10 kW
Commissioned 2026Commissioned 2027 (bill)
Rate7.70 ct/kWh5.2 ct/kWh
per year€77€52
Duration20 years3 years
Total, nominal€1,540€156
afterwards–1.5 ct bonus + market revenue, or €0

Over the full term that is a factor of ten. It sounds dramatic, but it looks different once you put self-consumption next to it: every kilowatt-hour you use yourself saves the energy price of your electricity tariff – it is on your bill. At an energy price of 30 cents, a self-consumed kilowatt-hour is worth almost four times as much as one exported in 2026, and almost six times as much as one exported in 2027.

The government justifies the abolition with exactly that argument: small systems are “often already economical without additional support due to lower costs, provided they can achieve high self-consumption shares”. The word that matters is provided. Anyone building in 2027 or later designs the system around self-consumption – or it does not pay off.

Is it worth rushing to build now?

The honest answer: the feed-in tariff alone is rarely the reason. But three situations argue for bringing forward a system you were planning anyway:

What argues against it is a hasty order with the first provider available because December is looming. A badly planned system costs more over 20 years than the difference between 7.70 and 5.2 cents.

What changes for the technology in the house

When exporting earns next to nothing, control becomes more important than the panels: when does the battery charge, when the car, when does the immersion heater run? This can be solved with local energy management, without a cloud and without new hardware for every task. My own PV runs with a Victron system and a Pylontech battery; the following articles show how the individual loads follow the surplus:

Frequently asked questions

Has the feed-in tariff already been abolished?

No. As of 30 September 2026 there is a government bill (printed paper 21/7867). The Bundestag held its first reading on 24 September and referred it to the Committee on Economic Affairs and Energy; the public hearing is scheduled for 5 October 2026. Nothing has been passed yet, and the bill may change during the process. It is intended to enter into force on 1 January 2027.

Will my existing PV system lose its feed-in tariff?

No. Under the transitional provision in the bill, installations commissioned before 1 January 2027 remain subject to the EEG as it stood on 31 December 2026. The tariff therefore continues on the terms under which the system was built, as a rule for 20 years from commissioning.

How much will new installations get from 2027?

Under the bill, a time-limited transitional payment: the uniform reference value of 6.2 cents minus 1 cent, i.e. 5.2 cents per kilowatt-hour fed in, for at most 36 months. In 2027 it is open to installations below 50 kW, in 2028 only below 25 kW, and in 2029 and 2030 below 7 kW. Balcony solar units are excluded. After that, the options are direct marketing, handing the power to the grid free of charge, or zero export.

What counts as commissioning by 31 December 2026?

The EEG defines commissioning as the first operation of the installation after it has been made technically ready for operation. The installation must be permanently mounted at its intended location together with the equipment needed to generate alternating current, i.e. the inverter. Modules stored in the basement or a missing inverter are not enough. Check with your grid operator beforehand how the date has to be documented.

Is solar still worth it without a feed-in tariff?

That depends almost entirely on self-consumption. Every kilowatt-hour you use yourself saves the energy price of your electricity tariff; every kilowatt-hour fed in earns at most 5.2 cents from 2027, and only for three years. The government justifies the step explicitly by saying that small systems with high self-consumption are economical without support. Battery, wallbox, heat pump or immersion heater therefore decide the calculation.

Sources

All information comes from the following documents, each with the date it was checked. The printed paper is a preliminary version and reflects a bill; only the promulgated law will be binding. All sources are in German.

This article describes a bill and is not legal or tax advice. Registering and connecting a PV system is reserved for a registered electrical contractor.