Easee and section 14a EnWG

With Easee, the route does not lead directly to the wallbox. The control command goes via a contact to a metering solution with an Equalizer, which distributes the limit to the chargers. Easee describes this in a detailed help article – including a statement that matters for planning: EEBUS is not supported for it.

Applies to
non-public Easee charging installations in Germany
Signal path
control box → potential-free contact → metering solution and Equalizer → chargers
Metering solution
Equalizer Amp up to 100 A · CVM E3 mini up to 250 A · Janitza UMG 604 Pro above
EEBUS
not supported for this configuration
Manufacturer source
Easee help article on section 14a, last updated 3 September 2026
Status
October 2026 · primary sources below, with the date each was checked
Author
Julian Haag, state-certified electrical engineering technician

The signal path

Easee describes the route in four steps: an external control device – “for example an FNN control box or a ripple control receiver” – provides the grid operator's request. A potential-free contact transmits the state to the metering solution. Metering solution and Equalizer provide the configured limit to the responsible primary chargers. And the chargers apply it for as long as the request is active.

For planning this means: Easee's documented section 14a route runs via metering solution and Equalizer, not directly to the charger. And: “EEBUS is not supported for this Easee section 14a configuration. Any other digital interface requires separately documented and approved project planning.”

Which metering solution

Easee metering solution by installation size (help article of 3 September 2026)
SolutionInstallation sizeConfiguration
Equalizer Ampup to 100 Aone control level in the Installer App; two to four control levels via Easee Support
CVM E3 miniover 100 A up to 250 AModbus configuration and matching project drawing
Janitza UMG 604 Proover 250 AModbus configuration and matching project drawing

With the Equalizer Amp, first clarify how many control levels the grid operator requires; the approved installation drawing follows from that.

The local connection

The Equalizer must be able to transmit the control value locally to the chargers. With one charging circuit this is possible via Easee Link RF, given reliable radio coverage. With several charging circuits, the Equalizer and all primary chargers must be on the same local Wi-Fi. Internet is not required for the local section 14a control path.

Easee warns against an obvious mix-up: “Wi-Fi is not the same as internet.” A cloud-offline status does not mean the local control path has failed – and a cloud-online status does not confirm that the Equalizer reaches every charger locally.

Easee: section 14a signal path and metering solution by installation size On the left, the signal path from top to bottom: control box or ripple control receiver, potential-free contact, metering solution with Equalizer, then via Link RF or Wi-Fi to the primary chargers. On the right, the metering solution by size: up to 100 amperes Equalizer Amp, 100 to 250 amperes CVM E3 mini, above 250 amperes Janitza UMG 604 Pro. Below, crossed out: EEBUS is not supported for this configuration. No internet is needed for the local path. control box or ripple control receiver potential-free contact metering solution + Equalizer primary chargers Link RF / Wi-Fi Metering by size up to 100 A Equalizer Amp 100 to 250 A CVM E3 mini above 250 A Janitza UMG 604 Pro EEBUS: not supported for this configuration No internet neededfor the local path
Based on Easee’s help article on section 14a (last updated 3 September 2026). Link RF is enough for one charging circuit; with several, the Equalizer and all primary chargers must be on the same local Wi-Fi.

Setup and testing

The order according to Easee: install metering solution and Equalizer according to the product instructions, wire the external control signal exactly according to the selected drawing, ensure the local communication path, configure “GPI Ripple Control” in the Installer App with the confirmed control values and contact logic – and then trigger a real control request.

The last step is the one that tends to get skipped in practice. Easee requires switching the real contact for each control level, checking that all affected charging circuits apply the value and return afterwards, and recording signal state, control level, local connection and resulting charging power in the commissioning report. “Do not just check an app or cloud status.”

How much power remains

Easee makes it clear: “4.2 kW is not a permanent charging limit”. Under direct control, the Bundesnetzagentur's ruling requires a minimum power of 4.2 kW to remain available in principle (clause 4.5.1); when several devices are controlled via an energy management system, the sum and simultaneity rules apply. Which value applies during curtailment is one of the control values entered during configuration.

Frequently asked questions

Is an Easee wallbox section 14a capable?

Yes, but not on its own. According to Easee, the control request runs from the control box or ripple control receiver via a potential-free contact to a metering solution with an Equalizer, which passes the limit on locally to the chargers. Up to 100 A that is the Equalizer Amp, above that a CVM E3 mini or a Janitza UMG 604 Pro.

Does Easee support EEBUS for section 14a?

No. Easee writes: “EEBUS is not supported for this Easee section 14a configuration.” According to Easee, any other digital interface requires separately documented and approved project planning.

Does Easee's section 14a control need internet?

No. According to Easee, the local control path needs no internet, but it does need a local connection between Equalizer and chargers: Easee Link RF with one charging circuit, a shared local Wi-Fi with several.

Sources

The manufacturer information comes exclusively from the manufacturer's own documents, each with its date and the date it was checked. Manufacturer documents change with every firmware release; what counts is the version valid at the time of installation. Quotations from German documents are our translation.

This article reproduces manufacturer information; it replaces neither Easee's documentation nor the technical connection conditions of your grid operator. Connection and registration are reserved for a registered electrical contractor. Haag Automation has no business relationship with Easee.